Published: 11:28, November 16, 2024 | Updated: 11:37, November 16, 2024
Onagawa nuclear reactor in northeastern Japan resumes power output after 13 years
By Xinhua
This photo shows the Onagawa nuclear power plant, operated by Tohoku Electric Power Company, Inc., in Onagawa, northeastern Japan, Oct 24, 2024. (PHOTO / KYODO NEWS VIA AP)

TOKYO - A reactor at the Onagawa nuclear plant in Miyagi Prefecture, northeastern Japan, has resumed power generation for the first time since the Fukushima nuclear disaster in March 2011, its operator said.

Tohoku Electric Power Company said that the Onagawa No. 2 reactor restarted power generation at 6 pm local time Friday.

ALSO READ: Takahama nuclear reactor becomes first in Japan to operate for 50 yrs

After an adjustment operation to check for any abnormalities while gradually increasing output, the reactor will be temporarily halted for equipment checks.

The reactor is expected to start full commercial operation in December, it added. The 825,000-kilowatt reactor, if operated at about 70 percent of its capacity for one year, is estimated to generate electricity equivalent to the power consumption of 1.62 million households, according to Tohoku Electric.

READ MORE: Japan starts 9th ocean discharge of Fukushima nuclear-tainted wastewater despite opposition

The No. 2 reactor was reactivated on Oct 29 but was halted on Nov 4 after an issue was found with a measurement device.

After the problem was fixed, the reactor was restarted again on Wednesday.

READ MORE: Japan starts 8th discharge of Fukushima nuclear-tainted wastewater

The three reactors at the Onagawa plant are of the same boiling water type as those at Tokyo Electric Power Company's Fukushima Daiichi nuclear plant, where the country's worst nuclear accident was triggered by the massive earthquake and tsunami on March 11, 2011.